In brief

  • Companies applying for e-MOVE RO funding can file their application without the technical connection approval, provided they prove they sent the documentation to the network operator before the call for projects was launched. The technical document is presented at the contracting stage.
  • The 5-year durability period is calculated from the last payment made under the project; under the previous wording it ran from the completion of implementation. The beneficiary’s four obligations during this period stay the same.
  • Electric ground power units for aircraft are funded only under sub-measure 1, and under sub-measure 3 the 75% rule for batteries now refers to the stored energy, that is, the energy the battery absorbs.

Who is affected: enterprises and communities preparing charging station projects for their own fleets or for public use, airport operators and ground handling service providers at airports, and the electricity distribution system operators that issue connection approvals.

Act: Order of the Minister of Transport and Infrastructure no. 1.161/2026 amending the annex to Order of the Minister of Transport and Infrastructure no. 1.318/2025 approving the State Aid Scheme for promoting infrastructure for zero-emission mobility in support of enterprises and communities (e-MOVE RO)
Published: Official Gazette of Romania, Part I, no. 961 of 18 November 2026, pages 15-16
In force from: 18 November 2026, the date of publication, as the order sets no other date

The Ministry of Transport and Infrastructure has amended the e-MOVE RO state aid scheme for the third time in three months. The scheme uses the Modernisation Fund to finance electric charging stations located outside the network of motorways, expressways and TEN-T national roads managed by the National Company for Road Infrastructure Administration (CNAIR). The scheme’s annex was replaced in full on 10 August 2026, and on 2 September 2026 Order no. 821/2026 rewrote Article 11, which lists the eligible investments. Order no. 1.161 of 17 November 2026, published in the Official Gazette of Romania (Monitorul Oficial) on 18 November 2026, changes four things: the connection documents required when the application is filed, the durability period, the eligible investments under each sub-measure and the power requirements for public stations.

The change with the most direct effect concerns the application file. Until now, the opportunity analysis had to include the solution sheet, the solution study or the technical connection approval, as the case may be. From 18 November 2026, an applicant that does not yet hold these documents may present proof that it sent the network operator the documentation needed to establish the connection solution, provided it did so before the call for projects was launched. The technical connection document becomes mandatory only at the contracting stage.

The order approves no new budget, opens no call for projects and leaves the ceilings unchanged. It was signed on behalf of the minister by Secretary General Marius Toader and cites Competition Council Opinion no. RG/12,524 of 5 August 2026.

What it changes in practice

For applicants, the connection requirement moves from the filing stage to the contracting stage. A project is no longer knocked out of the competition simply because the distribution system operator has not issued the approval in time, subject to one strict condition: the documentation must have been sent to the operator before the call is launched. A company that decides to apply after the launch and only then files the documentation with the operator cannot rely on this facility.

The durability period starts later. During those 5 years, the beneficiary may not cease the activity carried out with the funded asset, may not dispose of the assets, may not make a substantial change that undermines the objectives of the investment, and must ensure non-discriminatory public access to the charging infrastructure, including as regards tariffs, authentication and payment. Since the period now runs from the last payment, these obligations, together with the annual energy audit required by Article 11(6) throughout the durability period, extend over a longer interval.

For eligible investments, the effects differ by sub-measure:

  • Sub-measure 1 (charging infrastructure for a fleet, for the public or for both, with the related grid connection) remains the only route for buying electric or battery-electric ground power units (GPU) used to power the systems of parked aircraft. For each new unit, the applicant must scrap a GPU with a combustion engine within 60 days of commissioning.
  • Sub-measure 2 (stations for the company’s own fleet, with renewable generation and storage) loses funding for GPUs. The ceiling for the renewable installation now refers only to the maximum rated useful power of the charging infrastructure, without the reference to “capacitatea de realimentare” (refuelling capacity), which concerned a different type of infrastructure.
  • Sub-measure 3 (publicly accessible stations, with renewable generation and storage) keeps the rule that the renewable installation may exceed the station’s power by no more than 40%. The storage component must absorb each year at least 75% of its energy from the directly connected renewable installation.

At publicly accessible stations, each location must have at least 2 charging points of at least 150 kW in direct current and one point of at least 350 kW (DC HPC) where the opportunity analysis justifies it, that is, at locations where heavy-duty vehicles also charge. All public points accept the payment instruments widely used in the Union, including electronic payment through terminals.

What has changed compared with the previous situation

The comparison is with the text in force until 17 November 2026: Articles 9 and 10 as worded by Order no. 755/2026, and Article 11 as worded by Order no. 821/2026.

  • Art. 9(h), connection documents. The previous wording required the solution sheet, the solution study or the technical connection approval in the opportunity analysis, with no alternative. The new wording accepts, at filing, proof that the documentation was sent to the network operator before the call was launched, and defers the technical document until contracting.
  • Art. 10(3), durability. The 5 years used to run “de la finalizarea implementării proiectului” (from the completion of project implementation). They now run “de la ultima plată în cadrul proiectului” (from the last payment under the project). Points a)-d), with the beneficiary’s obligations, are carried over without any change.
  • Art. 11(2)(b), sub-measure 2. The ceiling for the renewable installation referred to “puterea maximă utilă nominală sau capacitatea de realimentare a infrastructurii de reîncărcare sau de realimentare” (the maximum rated useful power or the refuelling capacity of the charging or refuelling infrastructure). It now refers only to the maximum rated useful power of the charging infrastructure.
  • Art. 11(2)(c), sub-measure 3. The sentence on storage began with “În cazul sistemelor de stocare” (in the case of storage systems) and required the battery to absorb each year at least 75% “din energia electrică provenită din instalația” (of the electricity coming from the installation) using renewable sources. The new wording drops the condition and requires the battery to absorb at least 75% “din energia sa” (of its energy) from the renewable installation.
  • Art. 11(2)(d), GPUs for aircraft. They were eligible under sub-measures 1 and 2. They are now eligible only under sub-measure 1. The obligation to scrap within 60 days remains.
  • Art. 11(3), power at public stations. The previous text required “cel puțin un punct de 350 kW”, literally at least one point of that power. The new text requires “un punct de cel puțin 350 kW”, one point whose power is at least that figure, so the minimum shifts from the number of points to the power of the point. The rest of the paragraph, on smart charging and payment instruments, is carried over unchanged.

Advantages and disadvantages

What it improves

  • Projects are no longer rejected at filing because of a connection approval that the distribution system operator has not yet issued, even though the applicant requested the solution in good time.
  • The 75% rule for batteries refers to the energy the battery absorbs, so the photovoltaic installation can supply the station directly without being forced to route most of its output through storage.
  • The ceiling for the renewable installation under sub-measure 2 is read against a single benchmark, the power of the charging station.
  • The requirement of at least 350 kW for the HPC point matches the charging of heavy-duty vehicles, for which it was designed.

What remains a problem

  • The order does not say by when the technical connection document must be presented at contracting, nor what happens if the network operator has not issued it by then.
  • The actual length of the durability obligations depends on the date of the last payment, which is set by the paying authority, no later than 31 December 2030.
  • On the wording of the text, the non-discriminatory public access obligation applies to all beneficiaries, including those whose stations serve only their own fleet.
  • Airports that planned electric GPUs within projects with their own renewable generation must fit them under sub-measure 1.

Practical advice

  1. File the documentation for the connection solution with the distribution system operator now, before the call is launched. Keep the proof of sending, with a certain date, since it replaces the approval when the application is filed.
  2. Follow up the request with the operator until contracting. Without the technical connection document at that stage, the financing contract cannot be signed.
  3. Calculate the durability period from the last payment and budget for the annual energy audit over that whole interval, not just for 5 years from the completion of implementation, as the previous wording provided.
  4. If the project includes ground power units for aircraft, place it under sub-measure 1 and plan to scrap the combustion unit within 60 days of commissioning the new one.
  5. Under sub-measure 3, size the battery so that at least 75% of the energy it absorbs each year comes from the directly connected renewable installation, and keep the installation’s power within 140% of the station’s power.
  6. If you are preparing a station for your own fleet under sub-measure 2, ask for written clarification on the public access obligation during the durability period before signing the contract.

Frequently asked questions

Can I file the funding application without the technical connection approval?
Yes, if you have proof that you sent the network operator the documentation needed to establish the connection solution before the date the call for projects was launched. You present the technical connection document at the contracting stage.
From when is the 5-year durability period calculated?
From the last payment made under the project. Under the previous version of the scheme, the period ran from the completion of project implementation.
Does the order open a new call or bring additional money?
No. The order only amends the conditions of the e-MOVE RO scheme. It sets no new budget, leaves the ceilings unchanged and fixes no date for a call for projects.
What power must a publicly accessible station have?
Each location must have at least 2 points of at least 150 kW in direct current and one point of at least 350 kW (DC HPC) where the opportunity analysis justifies it, that is, at locations where heavy-duty vehicles can also charge. The infrastructure must support smart charging and accept electronic payment through terminals.
Can electric ground power units for aircraft still be funded under sub-measure 2?
No. From 18 November 2026, they are eligible only under sub-measure 1, with the obligation to scrap one GPU with a combustion engine for each new unit, within 60 days of its commissioning.
When do the changes apply?
From 18 November 2026, the date of publication in the Official Gazette of Romania, Part I, no. 961. The order sets no other date.

Errors and inconsistencies in the published text

  • Annex, Art. 10(3)(d), as worded by Art. I point 2 of the order. This point requires every beneficiary, throughout the durability period, “să asigure accesul publicului nediscriminatoriu la infrastructura de reîncărcare, inclusiv în ceea ce privește tarifele, metodele de autentificare și de plată” (to ensure non-discriminatory public access to the charging infrastructure, including as regards tariffs and authentication and payment methods). Yet the same scheme finances, under Art. 11(2)(b), infrastructure for company fleets (sub-measure 2), defines in Art. 6(u) infrastructure that is not publicly accessible as infrastructure used by the beneficiary “fără a fi pusă la dispoziția publicului larg” (without being made available to the general public), and in Art. 11(5) prohibits payment instruments at points intended exclusively for the beneficiary’s own fleet. A sub-measure 2 beneficiary can draw two conclusions from the text: either it must open its station to the public for 5 years, which contradicts the purpose of the funding, or point d) does not apply to it, even though the text makes no distinction. The order rewrites the paragraph in full and keeps point d) without delimiting its scope.

Editorial analysis

The order solves a real problem for applicants: the technical connection approval depends on the distribution system operator, and until now its absence at filing knocked the project out of the competition. The solution chosen, proof of a request sent before the call is launched, is balanced, since it keeps a test of seriousness. It remains unfinished, however: the text sets the point by which the approval must be requested, but not the deadline by which it must be obtained, so the risk of the operator’s delay moves from the filing stage to the contracting stage, with no rule for the case where the approval never arrives.

The most important change is also the least visible one, the 75% rule under sub-measure 3. The previous wording required the battery to absorb 75% “din energia electrică provenită din instalația” (of the electricity coming from the installation) using renewable sources. Read literally, a photovoltaic installation producing 100 MWh a year had to route at least 75 MWh through the battery and leave only 25 MWh for direct charging, so large-scale storage became mandatory. The new wording, “din energia sa” (of its energy), reverses the benchmark: a battery that absorbs 40 MWh a year must take at least 30 MWh from the panels, and the rest of the output can go straight to the station. Also under sub-measure 3, the condition “În cazul sistemelor de stocare” (in the case of storage systems) disappears, which suggests that storage is a mandatory part of the project, even though Art. 11(1)(d) still says that investments “pot integra” (may include) storage.

Moving the start of the durability period to the last payment has an effect that does not show from a reading of the order. Projects must be completed by 30 June 2030 at the latest, and the aid can be paid until 31 December 2030 (Art. 12(4) of the scheme), so the durability period of a project finished at the deadline ends between 30 June and 31 December 2035, depending on the date of the last payment. The deadlines imposed on the beneficiary are fixed, such as the 60 days for scrapping a combustion GPU, but the length of the longest obligation, including the annual energy audit, now depends on how quickly the authority pays, within the payment deadline of 31 December 2030.

The order cites Competition Council Opinion no. RG/12,524 of 5 August 2026, the same opinion on which Order no. 755/2026 of 6 August 2026 relied. 104 days passed between the opinion and the signing of the current order, and in the meantime the scheme was amended by Order no. 821/2026, whose preamble mentions no opinion at all. The text does not reveal whether the amendments of 17 November 2026 were examined by the Competition Council.

What should be changed

  • Limiting Art. 10(3)(d) to publicly accessible infrastructure. Wording along the lines of “in the case of publicly accessible infrastructure” would spare sub-measure 2 beneficiaries the risk of breaching a durability obligation that the nature of their project does not allow them to meet.
  • A deadline for the technical connection document. The scheme should state within how many days of notification of the result the document must be presented, and whether the deadline is extended when the delay lies with the operator. Applicants would then know in advance whether they could lose their place in the ranking.
  • Written notice of the date of the last payment. A notification to the beneficiary stating the day from which the durability period runs would make the end date of the obligations verifiable and would prevent disputes over when the beneficiary may freely dispose of the assets.
  • Aligning Art. 11(1)(d) with sub-measure 3. If storage is mandatory under sub-measure 3, the general rule should say so, rather than stating that investments “pot integra” (may include) storage. Applicants would know for certain whether a project without a battery is eligible.
  • Clarifying the phrase “acolo unde se justifică” (where justified) in Art. 11(3). The text can be read as referring only to the 350 kW point or also to the two 150 kW points. A separate sentence for each requirement would remove the doubt at evaluation.
  • Publishing a consolidated version of the scheme. The annex was replaced on 10 August, amended on 2 September and again on 18 November 2026. A consolidated text on the ministry’s website would let applicants work from a single version of the text.

Original text of the legal act

The text below is reproduced in Romanian, the official form of publication.

The full text, as published in the Official Gazette of Romania

Official Gazette of Romania no. 961 of 18 November 2026, pages 15-16 16 pages PDF, 107 KB the act starts on page 15

Open the official PDFDownload the PDF

The viewer is not shown on small screens. Use the buttons above to open or download the file.

This article is for informational purposes only and does not constitute legal advice. For specific situations, consult a licensed attorney or tax advisor.