In brief
- The state has set the compensation for the land needed to expand the Podișor and Bibești gas compression stations, part of a project supplying power plants at Mintia, Ișalnița and Turceni, at 205,640 lei.
- The amount is paid by Transgaz to the owner of the land expropriated for this project of national interest.
- It concerns the landowners affected by the project and, indirectly, local authorities and industrial consumers in the area, who benefit from additional gas transmission capacity.
Published: Official Gazette of Romania (Monitorul Oficial) No. 649 of 6 August 2026
In force from: 6 August 2026
The Ministry of Economy, Digitalisation, Entrepreneurship and Tourism has approved an expropriation value of 205,640 lei for the land needed to expand the Podișor and Bibești compression stations. Order No. 1.188/2026, published in the Official Gazette of Romania No. 649 of 6 August 2026, sets the amount that the National Natural Gas Transmission Company “Transgaz” will pay as just compensation to the landowner, as part of a project declared of national importance by Government Decision No. 760/2025.
The project aims to increase transmission capacity in the National Transmission System for supplying natural gas to the combined-cycle power plants at Mintia, Ișalnița and Turceni, as well as to local authorities and other industrial consumers in the area. The compensation amount was calculated based on two separate valuation reports, one for each station, drawn up by ANEVAR-authorised appraisers and endorsed by Transgaz’s Technical-Economic Council.
What it changes in practice
For the owner of the land concerned, the order triggers the actual payment of the 205,640 lei compensation, arranged by the ministry’s General Directorate for Institutional Management and its Economic Directorate. The amount represents the “just compensation” to which any owner expropriated for public use is entitled under Law No. 255/2010.
For the national natural gas transmission system, completing this administrative step allows work to continue on expanding the Podișor and Bibești compression stations, considered essential for supplying natural gas to the combined-cycle power plants at Mintia, Ișalnița and Turceni, as well as other industrial consumers and local authorities in the area.
What has changed compared with the previous situation
- Expropriation value officially approved: before this order, the exact compensation amount was not set by a legal act; it is now fixed at 205,640 lei.
- Two separate valuation reports: the amount covers both the Podișor station land and the Bibești station land, each valued separately.
- Legal basis for payment: Transgaz can now make the payment to the landowner, through the ministry’s General Directorate for Institutional Management and its Economic Directorate.
Advantages and disadvantages
What it improves
- It unlocks payment of a concrete compensation, calculated by authorised appraisers, for the owner of the land affected by the project.
- It allows an energy infrastructure project of national interest to continue, which supports natural gas supply to three major power plants.
- It establishes a transparent procedure, with an ANEVAR valuation and technical-economic endorsement, for calculating the compensation.
What remains a problem
- The order does not specify the exact surface area of the expropriated land at each of the two stations, information relevant to assessing whether the amount is adequate compensation.
- No concrete deadline is mentioned by which the payment must be made to the owner.
- The document remains technical and administrative, hard for the general public to follow without knowledge of expropriation procedures in the energy sector.
Practical advice
- If you are the owner of the land covered by this order, check with Transgaz and the ministry on the status of the 205,640 lei compensation payment, using the order number as a reference.
- If you own land near similar energy infrastructure projects, inform yourself in advance about the expropriation procedure set out in Law No. 255/2010, so you know what to expect.
- Keep all documents related to the valuation of your land, useful in case of any future dispute over the compensation amount.
- Follow the Official Gazette of Romania for similar orders if you live near the Mintia, Ișalnița or Turceni power plants, where several gas transmission network expansion works are planned.
Frequently asked questions
How much is the compensation approved by this order?
Who pays the compensation?
Why is the expropriation necessary?
How was the compensation amount calculated?
Who is responsible for the accuracy of the data in the order?
Original text of the legal act
The text below is reproduced in Romanian, the official form of publication.
The full text, as published in the Official Gazette of Romania
Official Gazette of Romania no. 649 of 6 August 2026 16 pages PDF, 131 KB
Open the official PDFDownload the PDF
The viewer is not shown on small screens. Use the buttons above to open or download the file.
This article is for informational purposes only and does not constitute legal advice. For specific situations, consult a licensed attorney or tax advisor.