In brief
- The works on the group of buildings of the Monastery of Saint John the New of Suceava are being revalued: the total value rises from 100,164,000 lei, the sum approved in 2021, to 136,248,000 lei, that is 36,084,000 lei more, 36.0% up.
- Of the new value, 135,515,000 lei come from public money, from the State budget through the budget of the Ministry of Development, Public Works and Administration and through the National Investment Company, and 733,000 lei from the monastery’s own revenues. The beneficiary is a monastery; the main payer is the State budget.
- Still to be carried out are 73,218,000 lei over 12 months, and this part is, in its entirety, public money.
Published: Official Gazette of Romania (Monitorul Oficial), Part I, no. 835 of 1 October 2026, pages 9-10
In force from: 1 October 2026
The consolidation of the group of buildings of the Monastery of Saint John the New of Suceava reaches 136,248,000 lei, that is 36,084,000 lei more than the sum approved in November 2021. Government Decision no. 783/2026, published in the Official Gazette of Romania, Part I, no. 835 of 1 October 2026, reapproves the technical and economic indicators of the investment objective, that is it officially rewrites the figures on the basis of which the money is spent. The Government had also redone the arithmetic of a public investment two days earlier, when it topped up the expropriation compensation for the railway between Cluj-Napoca and Oradea.
The decision has three short articles, and all the substance sits in the annex. The holder of the investment is the Ministry of Development, Public Works and Administration. The beneficiary is the National Investment Company „C.N.I.” S.A. for the duration of the works, and the Monastery of Saint John the New of Suceava once they are finished. The site is in the city of Suceava, 2 Ion Vodă Viteazul Street.
The group of buildings is a historic monument, and the church of Saint George inside it forms part of the UNESCO World Heritage, in the series of churches of Moldavia. The annex expressly requires seismic protection of the objective in accordance with Standard P100-3/2013 and Methodology MP 025-04, on the terms of Law no. 422/2001 on the protection of historic monuments.
What it changes in practice
The first effect is the new spending ceiling. The total value of the investment, including VAT, is 136,248,000 lei, of which construction and assembly 85,753,000 lei. The rest, 50,495,000 lei, covers everything that is not the works themselves: design, technical assistance, charges, fittings. The figures are expressed in prices valid as at 1 August 2026, at an exchange rate of 1 euro = 5.0772 lei, so the whole investment is worth about 26.8 million euros.
The second effect is the split of the source. The Ministry of Development, Public Works and Administration, through the National Investment Company, finances 135,515,000 lei, and the monastery 733,000 lei from own revenues. The monastery’s contribution represents 0.54% of the total. Everything to do with construction and assembly, that is the 85,753,000 lei, falls entirely on the public side, because the monastery’s share is 0 lei under that heading.
The third effect is the one that shows where the works stand. The total value of the remaining works is 73,218,000 lei, of which construction and assembly 45,672,000 lei. Subtracting from the total, it follows that works of 63,030,000 lei have already been carried out, that is 46.3% of the recalculated investment. And the remaining works are financed exclusively from the budget: the 73,218,000 lei appear in full against the ministry, while against the monastery stands 0.
The fourth effect is the time limit. The annex provides for a duration of the remaining works of 12 months. It is the only duration in the act, because a total duration of the investment is no longer mentioned.
The fifth effect concerns capacities and responsibility. The objective has a built-up area of 2,920.20 square metres and a gross floor area of 5,895.20 square metres. Article 3 of the decision places responsibility for the way the sums are used on the Ministry of Development, Public Works and Administration, through the National Investment Company.
What has changed compared with the previous situation
The indicators had been approved by Government Decision no. 1.224 of 17 November 2021, published in the Official Gazette of Romania, Part I, no. 1105 of 19 November 2021. At that time the total value was 100,164,000 lei, of which construction and assembly 60,892,000 lei, with 99,182,000 lei from the ministry and 982,000 lei from the monastery, in prices valid as at 10 July 2021, at an exchange rate of 1 euro = 4.9281 lei.
The difference, in figures: the total value rises by 36,084,000 lei, that is 36.0%. The construction and assembly part rises faster than the total, by 24,861,000 lei or 40.8%, while the part that is not works rises by 11,223,000 lei or 28.6%. The public contribution climbs from 99,182,000 to 135,515,000 lei, by 36.6%.
Only one figure falls: the monastery’s contribution, from 982,000 to 733,000 lei, 249,000 lei or 25.4% less. Since its share of the remaining works is 0, the entire sum still to be spent, 73,218,000 lei, comes from public money.
The capacities have changed too, upwards, but only a little: the built-up area rises from 2,865.20 to 2,920.20 square metres, by 55 square metres, and the gross floor area from 5,636.20 to 5,895.20 square metres, by 259 square metres. The increase in value therefore does not come from a much larger building.
The most visible change of form is in the calendar. The 2021 annex had the investment phased over the years, 43,164,000 lei in year one, 33,000,000 lei in year two and 24,000,000 lei in year three, and an implementation period of 36 months. The 2026 one no longer has an annual schedule and no longer has a total duration. It has only the duration of the remaining works, 12 months. From the approval of the indicators to their reapproval, 4 years, 10 months and 14 days went by.
The same mechanism was used in November 2026 for another CNI investment: under Government Decision no. 969/2026, the new stadium in Târgoviște costs 22% more, at 425 million lei.
Advantages and disadvantages
What it improves
- The works can go on. Without updated indicators, a site where prices have risen above the approved value comes to a stop, and at a historic monument a stoppage brings further decay.
- The annex adds up exactly: 135,515,000 plus 733,000 make precisely 136,248,000 lei, and 73,218,000 plus 0 give precisely the remaining works. It can be checked without any further documents.
- The duration of the remaining works, 12 months, is a written target, not a vague formula of the „until completion” kind.
- Responsibility for the use of the sums is named in Article 3, on the ministry and on the National Investment Company, not left with the final beneficiary.
- Seismic protection is required expressly, through Standard P100-3/2013 and Methodology MP 025-04, on the basis of Law no. 422/2001. At a building in the World Heritage, the condition is not a formality.
What remains a problem
- The increase of 36,084,000 lei is not explained in the act. The annex gives the final figure, not the reasons that led to it, even though the difference amounts to more than a third of the initial investment.
- The annual schedule disappears. With it goes the possibility of checking, from one year to the next, whether the pace of execution matches the money allocated.
- There is no total duration of the investment. At 46.3% carried out after almost five years, the 12 months of remaining works say how much longer it will take from now, not how long it will have taken in all against the 36 months promised in 2021.
- The monastery’s contribution falls from 982,000 to 733,000 lei and has already been spent, so everything that follows is public effort. The act does not show why the beneficiary’s share was reduced at precisely the moment when the total cost rose.
- The annex says „inclusiv TVA”, including VAT, without the rate used, even though the 2021 annex stated 19%. Without the rate, the comparison between the two totals mixes the rise in the cost of the works with the change of tax.
Practical advice
- Remember the reference figure for any future check: 136,248,000 lei total value, of which 85,753,000 lei construction and assembly, in prices as at 1 August 2026.
- Do not compare the two totals directly without taking the VAT rate into account. The first sum includes VAT at 19%, and the standard rate rose to 21% from 1 August 2025.
- If you are following the state of the works, use the „value of the remaining works”, not the total value. The difference between them, 63,030,000 lei, shows how much had been carried out by 1 August 2026.
- For contracts and procurement, the document that counts is the annex, not the press releases. It is what fixes the value, the construction and assembly part, the capacities and the duration.
- The 12-month time limit runs for the remaining works. If by the autumn of 2027 the works are not finished, a fresh reapproval of indicators will follow, like this one.
- When looking for the earlier act, its number is 1.224/2021, published in the Official Gazette of Romania, Part I, no. 1105 of 19 November 2021. That is where the figures for the comparison sit.
Frequently asked questions
How much do the works cost now?
By how much has it risen since the first approval?
Who pays?
What does „reapproval” of the indicators mean?
How much longer will it take?
How much has been done so far?
From when does the decision apply?
Editorial analysis
The act does what has to be done: a consolidation site at a monument in the World Heritage cannot stand still because a piece of paper from 2021 shows a sum that 2026 prices have overtaken. The problem is not the increase, it is what cannot be seen around it. The first observation that does not come out of reading the act: compared in euros rather than in lei, the two values rise by less than it seems. At the exchange rate written in each annex, the investment goes from about 20.3 million euros, in 2021, to about 26.8 million euros, that is 32.0% up, not 36.0% up. Four points of the rise in lei are the depreciation of the currency, not additional works.
The second observation concerns tax. The 2021 document said „inclusiv TVA 19%”, including VAT at the rate then in force. The 2026 document says only „inclusiv TVA”, including VAT, and between the two documents the standard rate climbed to 21%, from 1 August 2025, by Law no. 141/2025. If the new value is calculated at 21%, then excluding VAT the investment goes from 84,171,000 to 112,602,000 lei, that is a rise of 33.8%, not of 36.0%. About 2.2 percentage points of the announced difference are therefore the change of rate. Omitting the rate breaches no rule, but it spoils the only comparison that matters to the payer.
The third observation comes out of comparing the two legal bases. The 2021 decision was founded on Article 42(1)(a) of Law no. 500/2002 on public finance, the provision that gives the Government the approval of technical and economic documentation for values above 28 million lei. The 2026 decision invokes Article 42(2), which concerns public investment carried out on the basis of external credits contracted or guaranteed by the State. There is no external credit in these works: Article 2 lists the State budget, the monastery’s own revenues and other lawfully established sources. The Government’s competence is not affected, because 136,248,000 lei exceed the threshold in paragraph (1)(a) in any event, so the outcome stays the same. The reference remains wrong nonetheless and, having been changed from the act it replaces, does not look like a simple drafting carry-over.
The fourth observation concerns the calendar. The old annex had execution split over three years, with sums for each, and an implementation period of 36 months. The present one has neither a schedule nor a total duration, only 12 months of remaining works, at a stage of 46.3% of the recalculated value, 4 years and 10 months after the first approval. The combination of the two provisions says more than either on its own: in half the original time, more than half the investment is to be carried out.
What should be changed
- The VAT rate, written into the annex. A single figure next to the words „inclusiv TVA”, including VAT, as there was in 2021. Without it, any comparison between two reapprovals mixes the rise in the cost of the works with tax changes.
- The previous value and the difference, shown in the act. At a reapproval, the annex should contain a line with the value approved by the previous decision and with the difference, in lei and in percentages. The reader now learns the new figure and has to look up the 2021 act himself in order to understand what happened.
- The reason for the increase, by category. Construction and assembly rose by 40.8%, and the rest by 28.6%. A note separating price indexation, additional works and fittings would turn the reapproval from a figure into an explanation.
- A return to the annual schedule. Without the sums for each year, no one can check whether the pace of execution matches the money allocated. The schedule existed in 2021 and there is no reason for it to disappear at precisely the act that raises the value.
- A total duration of the investment, alongside the duration of the remaining works. The 12 months say how much longer it will take. The total duration would say by how much the 36-month term from 2021 has been exceeded, and that is the information showing whether the investment is under control.
- Correction of the legal basis to Article 42(1)(a) of Law no. 500/2002. The outcome does not change, but an act invoking the rule for external credits at an investment financed from the budget creates needless uncertainty at the first inspection.
Original text of the legal act
The text below is reproduced in Romanian, the official form of publication.
The full text, as published in the Official Gazette of Romania
Official Gazette of Romania no. 835 of 1 October 2026, pages 9-10 16 pages PDF, 116 KB the act starts on page 9
Open the official PDFDownload the PDF
The viewer is not shown on small screens. Use the buttons above to open or download the file.
This article is for informational purposes only and does not constitute legal advice. For specific situations, consult a licensed attorney or tax advisor.