In brief
- The preparation loan the World Bank had granted Romania for the „Cartierul pentru justiție” project has been cancelled, and the loan account closed on 30 November 2025.
- The Bank cancelled 440,733.66 dollars that were never used, and Romania is repaying what it had already drawn, in ten half-yearly instalments, from 1 June 2026 to 1 December 2030.
- The total to be repaid is 2,266,477.56, of which 2,059,266.34 is principal and 207,211.22 accrued interest. Payment comes from the budget of the Ministry of Finance.
Published: Official Gazette of Romania (Monitorul Oficial) no. 702 of 25 August 2026
In force from: 25 August 2026
The „Cartierul pentru justiție” project, conceived as a judicial campus for the courts of Bucharest, is left without its World Bank preparation advance: the money that was never used has been cancelled, the account has been closed, and the State has to give back what it spent. Government Decision no. 640/2026, published in Official Gazette of Romania no. 702 of 25 August 2026, approves the exchange of letters that sealed the closure. It is the Executive’s second move in recent months on borrowing from international financial institutions, after the emergency response manual likewise agreed with the World Bank.
The advance had been granted through a letter agreement signed in Brussels on 30 May 2019 and in Bucharest on 6 June 2019, ratified by Law no. 261/2019. A project preparation advance, in World Bank language, finances the studies, the design work and the documentation needed before a large loan is signed.
The amendments approved now are in fact four letters: the Bank’s letter of 4 December 2025, the Ministry of Finance’s reply of 23 December 2025, the Bank’s payment notice of 9 April 2026 and the ministry’s confirmation of 24 April 2026.
The next day, in Official Gazette of Romania no. 708, there also appeared the decision closing the main loan for judicial services, with an undrawn balance of 3,724,365.32 euro cancelled by the same bank.
What it changes in practice
The first effect is the cancellation. Through the letter of 4 December 2025 the Bank announced the cancellation of 440,733.66 dollars from the loan account, and the ministry confirmed receipt on 23 December 2025.
The second effect is the closing of the account, which took place on 30 November 2025. From that moment on, no further part of the advance can be drawn.
The third effect is the repayment schedule. Annex no. 1 to the letter of 9 April 2026 sets ten half-yearly instalments, on 1 June and 1 December of each year, between 2026 and 2030.
The fourth effect concerns the amounts. Each instalment is 205,926.00 in principal plus 20,721.12 in accrued interest, that is 226,647.12. The last instalment, the one due on 1 December 2030, has a slightly larger principal, 205,932.34, and therefore a total of 226,653.46.
The fifth effect is about the total. The schedule shows 2,059,266.34 in principal, 207,211.22 in accrued interest and 2,266,477.56 in all.
The sixth effect is the source of payment. Article 2 of the decision states that the accrued interest is paid from the State budget, through the budget of the Ministry of Finance, the „General Actions” chapter, in accordance with the implementing rules for Government Emergency Ordinance no. 64/2007 on public debt.
The seventh effect has to do with the calendar. The first instalment fell due on 1 June 2026, that is, before the decision was published. The payment notice for it had already been sent on 9 April 2026.
What has changed compared with the previous situation
The first change is the status of the financing. From 2019 to 2025 the advance was available for preparing the project. It no longer is.
The second change is the nature of the obligation. What was an advance still to be drawn becomes a debt to be repaid, with a fixed schedule and half-yearly due dates.
The third change concerns the amount left unused. The 440,733.66 dollars that were cancelled can no longer be used, and if the project comes back it will need fresh financing.
The fourth change is an accounting one. The accrued interest, reflected in the aggregate balance under the letter agreement, is now paid under the rules on public debt, not out of the project budget.
What does not change is the legal basis. The letter agreement ratified by Law no. 261/2019 remains in force, and the amendments are approved on the basis of Article 6(2) of that same law.
One arithmetical observation, which can be checked in the table: the ten individual instalments add up to 2,266,477.54, two cents less than the printed total of 2,266,477.56. It is a rounding difference, not a substantive error.
Advantages and disadvantages
What it improves
- The situation becomes clear: the loan no longer hangs over the State as an open obligation with an uncertain schedule.
- The repayment schedule is public, with exact dates and amounts for every due date.
- The unused amount is cancelled, so the State pays no fees on money it never drew.
- The source of payment is set out expressly, the budget of the Ministry of Finance, so it does not depend on the budget of a line ministry.
- The instalments are small in budget terms, under a quarter of a million every six months.
What remains a problem
- The State is repaying more than two million for the preparation of a project that was never built.
- The decision says nothing about why the advance was cancelled, nor about what happens to the project from here on.
- The first instalment fell due on 1 June 2026, and the approval comes almost three months after that date.
- The 440,733.66 dollars that were cancelled are preparation money that will no longer be available if the project is revived.
- The amortisation schedule does not repeat the currency on each line, and the reader has to work it out from the cancellation letter, where the amount is expressed in dollars.
Practical advice
- If you are following the „Cartierul pentru justiție” project, note the reference date: the loan account closed on 30 November 2025. Any revival of the project will require fresh financing.
- For the full schedule, open the official edition attached to this article. Annex no. 1 contains all ten due dates, with principal and interest shown separately.
- If you work in public debt management, note the legal basis for payment: points 5.3.1(d) and 5.7 of the implementing rules approved by Government Decision no. 1.470/2007.
- The figures in the schedule are easy to check: nine equal instalments plus a slightly larger one at the end. The two cent difference from the printed total is a rounding.
- If you want the full background, look up Law no. 261/2019, the act that ratified the 2019 letter agreement.
- Keep in mind the distinction between the preparation advance and the loan itself. The advance finances the paperwork, not the construction.
Frequently asked questions
What is „Cartierul pentru justiție”?
Has the whole loan been cancelled?
How much does the State have to pay?
When are the instalments due?
What money is it paid from?
What are the amendments approved by the decision?
Is the project still going ahead?
Errors and inconsistencies in the published text
- Annex 1, the repayment schedule: the „Dobândă acumulată” column, accrued interest, does not close, and the difference carries over into the „Total” column. The ten rows of that column each carry 20,721.12, so their sum is 207,211.20. The printed total is 207,211.22, two cents more. The same difference shows up in the last column: the nine instalments of 226,647.12 plus the final instalment of 226,653.46 come to 2,266,477.54, while the total row shows 2,266,477.56. The figures reveal how it happened: total accrued interest, 207,211.22, divided by ten due dates gives 20,721.122, and the value was truncated to 20,721.12 on every row. The total row is correct in itself, because 2,059,266.34 plus 207,211.22 give exactly 2,266,477.56, so the mistake lies in the way the amount is spread: one instalment ought to have carried 20,721.14, just as the last principal instalment already carries 205,932.34, which is the rounding adjustment on the principal side. As printed, anyone paying exactly the amounts shown on the rows still owes two cents at the end of the schedule.
Editorial analysis
The decision opens nothing, it closes. It puts on record that the line of financing the World Bank had made available to Romania in 2019 to prepare the „Cartierul pentru justiție” ran out without the project ever reaching the stage of the loan proper. The figures tell the story better than any commentary: the advance was exactly 2,500,000 dollars, because the amount drawn and still to be repaid, 2,059,266.34, plus the balance cancelled on 30 November 2025, 440,733.66, come to precisely that. In other words, eight tenths of the advance went on documentation, and the rest was cancelled when the account was closed. From 1 June 2026 to 1 December 2030 the State pays back the part that was spent, in ten half-yearly instalments.
The structure of the schedule is worth explaining, because it does not look like an ordinary loan. The interest does not fall as the principal is repaid, it stays fixed, 20,721.12 at every due date. The reason is that no interest is charged on the outstanding balance; what is spread out is the interest already accrued by the time the account was closed, 207,211.22, divided into ten equal parts. That way of dividing is also where the two cent difference in the total row comes from. The same annex, though, has a more serious gap than the rounding: not one column carries the currency. That dollars are meant can be worked out only from the Bank’s letter of 4 December 2025, the single place in the act where USD appears, and payment is made from the State budget, in lei, at an exchange rate the act neither fixes nor points to.
The second thing that catches the eye is the institutional calendar. The exchange of letters was completed on 24 April 2026, and the first instalment fell due on 1 June 2026. The decision that approves the amendments and that, in Article 2, settles where the accrued interest is paid from, was adopted on 20 August and published on 25 August 2026. Between the due date and the legal basis for payment lie almost three months in which the Ministry of Finance either paid without the decision being in force, or did not pay. The act does not say which of the two happened and carries no mention of any late payment interest, although the schedule is issued by the creditor and the due dates are fixed.
What is left, finally, is the complete silence about the object. The 2,059,266.34 dollars drawn financed studies, design work and documentation for a judicial campus in Bucharest. The decision does not say what was produced with that money, nor who holds the result, nor whether the documentation is still usable if the project comes back in some other form. An act that closes a preparation financing ought to leave exactly that information behind, because it is the only thing that can turn a lost expense into an asset.
What should be changed
- An annex with an inventory of the documentation paid for out of the advance. The decision ought to list the studies and designs financed from the 2,059,266.34 dollars drawn, naming who holds them and where they can be consulted. In practice, a revival of the project would start from what already exists, and the public could see what it bought with this money.
- The currency and the exchange rate, written into the schedule. Annex 1 ought to carry the currency on every column and to say at what rate the amounts are converted when they are paid from the State budget. In practice, the payment made by the ministry could then be compared row by row with the creditor’s schedule.
- A deadline for approving the amendments, tied to the first due date. Where an exchange of letters fixes a payment schedule, approval by Government decision ought to come before the first due date, not three months after it. In practice, the budgetary basis would exist at the moment the money has to be paid.
- A statement about the payments already made. The act ought to say whether the instalment due on 1 June 2026 was paid and on what terms. In practice, it would then be known whether the State has run up late payment costs on a schedule the creditor treats as firm.
- A public record of the preparation advances in progress. The Ministry of Finance could publish periodically the list of advances of this kind, with the amount contracted, the amount drawn and the state of each one. In practice, the cancellation of a 2.5 million dollar line would no longer become public only through a decision appearing nine months after the account was closed.
Original text of the legal act
The text below is reproduced in Romanian, the official form of publication.
The full text, as published in the Official Gazette of Romania
Official Gazette of Romania no. 702 of 25 August 2026 16 pages PDF, 159 KB the act starts on page 3
Open the official PDFDownload the PDF
The viewer is not shown on small screens. Use the buttons above to open or download the file.
This article is for informational purposes only and does not constitute legal advice. For specific situations, consult a licensed attorney or tax advisor.
