In brief

  • The Government has set out what a company building wind farms in the Black Sea pays the State: a royalty of 0.75% of the revenue from commercial operation, plus two area-based fees.
  • The fees are 800 euro per square kilometre per year during the development stage, the one in which construction takes place, and 1,500 euro per square kilometre per year during the operating stage, indexed annually to euro-area inflation.
  • During the exploration stage nothing is due: the first payment obligation arises only when the development approval is issued, and the royalty, which brings in the bulk of the money, starts running only once the farm sells electricity.
Act: Government Decision no. 688/2026
Published: Official Gazette of Romania (Monitorul Oficial) no. 731 and no. 731 bis of 31 August 2026
In force from: 31 August 2026, and the royalty and fees from 30 September 2026

Four days after putting the three Black Sea wind perimeters on the map, the Government has also said what they cost. Government Decision no. 688/2026, published in Official Gazette of Romania no. 731 of 31 August 2026, with the implementing rules in edition no. 731 bis of the same day, approves the rules under which the Ministry of Energy will put the perimeters out to tender and sets the royalty and the fees owed to the State. It comes straight after the decision by which the three perimeters open to concession, 948 km² and 3,100 MW, were given exact coordinates.

The two acts have to be read together. The first says where building is allowed, the second says how one gets there and what is paid. Without them, Law no. 121/2024 on offshore wind energy remained a framework with no application: the State could not organise a tender and an investor could not cost a project, because neither the area nor the price of the concession was known.

The financial obligations are built in three tiers, tied to the stages of the project. During the exploration stage, running from the entry into force of the concession contract to the issue of the development approval, the concessionaire owes neither royalty nor area fee. During the development stage, that is from the development approval to commercial commissioning, the fee of 800 euro per square kilometre per year is due, calculated on the area where works are actually carried out. During the operating stage both change: the fee rises to 1,500 euro per square kilometre per year, calculated on the built-up area and on the area taken up by the submarine connection cables, and on top of it comes the royalty of 0.75% of revenue.

The operating rules were published the same day: the development approval, the decommissioning approval, operational safety and the acceptance of the works.

What it changes in practice

The first effect is that an investor can now put figures into a business plan. Until 31 August the cost of the concession was an unknown; it now has three components, all expressed as closed formulas, and the unit values are written into the methodology rather than left to the contract.

The second effect is the payment calendar. The royalty and the two fees are tax claims, they are declared to the competent tax authority and paid annually, by 30 March of the year following the one for which they are due. The concession contract may add clauses on record-keeping and proof of payment, but it cannot set deadlines other than those laid down by law.

The third effect concerns indexation. The values of 800 and 1,500 euro are indexed annually, starting with the second calendar year of application, using the harmonised index of consumer prices for the euro area published by Eurostat. The fee is set in euro and paid in lei, at the exchange rate of the National Bank of Romania.

The fourth effect is one of waiting. The rules do not approve the support scheme. Article 52 says explicitly that the scheme provided for in Article 8(2) to (4) of Law no. 121/2024 is approved separately, by a further Government decision, in compliance with State aid rules. In other words, the part that says how much the State pays the producer does not yet exist, although the part that says how much the producer pays the State has arrived.

The fifth effect is monitoring. The concessionaire sends the Ministry of Energy quarterly reports during the exploration and development stages and an annual report during operation, by 31 March. The Ministry may carry out on-site checks, announced in advance, with the concessionaire entitled to raise objections. How far the State may move the price of a concession once it is signed was settled in September 2026, when the Court accepted that a mining royalty can be raised for licences already in force.

What has changed compared with the previous situation

Law no. 121/2024 had established that a royalty is due for commercial operation and that two area-related fees are payable, but it left the amounts to the Government. This is the decision that fills the gap, and the practical difference is between a framework nobody could assess and one in which every square kilometre has a price.

The way tenders are organised also changes. Procedures are launched for the perimeters on the list approved by Government Decision no. 664/2026, and the moment each one is launched is decided by the Ministry of Energy, on the basis of four criteria written into the rules: the availability of the approved perimeters, grid connection capacity, national renewable energy targets, and the applicable technical and economic conditions. None of them comes with a deadline.

Part of the decision does not take effect on publication. Article 4 postpones by 30 days the entry into force of Articles 47 to 51 of the rules and of the annex containing the methodology, that is precisely the articles that set the royalty, the fees and the way they are calculated. They apply from 30 September 2026. The rest of the rules, including the concession procedure, apply from 31 August 2026.

An explicit regime for projects carried out in phases also appears. Each phase has its own moment of transition from the development fee to the operating fee, and the royalty is due on the revenue of each phase brought into service, not on the farm as a whole.

Advantages and disadvantages

What it improves

  • The cost of the concession can be quantified in advance: one percentage rate and two unit values, all written into the act rather than negotiated in the contract.
  • The exploration stage remains free of fees, which lowers the investor’s risk at precisely the point where it is not yet known whether the project will go ahead.
  • The operating-stage fee is calculated on the area actually built on, not on the whole area under concession, so it does not penalise the space left empty between turbines.
  • Indexation to the euro-area harmonised index protects the real value of the State’s receipts on a concession that runs for decades.
  • Phased projects have rules of their own, so a farm commissioned piece by piece does not pay the operating fee on what is not yet producing.

What remains a problem

  • The support scheme, the part that decides whether projects are bankable, has not been approved and has no deadline.
  • The moment each tender is launched is left to the discretion of the Ministry of Energy, with no deadline and no obligation to announce a calendar.
  • The amount of the financial guarantees, including the one covering environmental damage, is not set in the act but left to the tender documentation.
  • The articles setting the fees and the one imposing the model contract refer to numbered annexes that do not exist in the act.
  • The date of the exchange rate used to convert the fees from euro into lei is written in square brackets, like a drafting marker left in the text.

Practical advice

  1. If you are preparing an offshore project, calculate the three obligations separately. The development fee applies to the area on which works are carried out under the development approval, not to the whole area under concession.
  2. Bear in mind that the area used in the operating stage also includes the zone taken up by the underwater electricity cables connecting to the connection points, even where these lie outside the area under concession.
  3. Budget for indexation. The values of 800 and 1,500 euro rise every year, from the second year of application, in line with the harmonised index of consumer prices for the euro area published by Eurostat for the previous year.
  4. Mark 30 March as the annual deadline for declaring and paying, for the previous year. It is a statutory deadline, and the concession contract cannot change it.
  5. Do not build your financial plan on the support scheme. It has not been approved, and the rules say expressly that they do not establish one.
  6. Keep complete records of the elements underlying the calculation. The Ministry of Energy may ask for them at any time, and the tax authorities have inspection powers of their own, separate from the Ministry’s.
  7. If the project is carried out in phases, ask for each phase to be clearly defined in the concession contract. That is where the date of commercial commissioning is set, the date that moves the fee from 800 to 1,500 euro per square kilometre.

Frequently asked questions

What does a Black Sea wind farm pay the State?
Three things: a royalty of 0.75% of the revenue obtained from commercial operation, a fee of 800 euro per square kilometre per year during the development stage and a fee of 1,500 euro per square kilometre per year during the operating stage. The two area fees are indexed annually to euro-area inflation; the royalty rate stays fixed.
When does the first payment start running?
When the development approval is issued. Until then, throughout the exploration stage, neither royalty nor area fee is due.
What area are the fees calculated on?
During the development stage, on the area where construction works are carried out, as it appears from the technical documentation approved through the development approval. During the operating stage, on the area actually occupied by works and installations, plus the area of the underwater cables connecting to the connection points.
When are they paid?
Annually, by 30 March of the year following the one for which they are due. They are tax claims and are administered under the Fiscal Procedure Code.
When can the tenders start?
Procedures are organised for the perimeters on the list approved by Government Decision no. 664/2026, and the moment each one is launched is set by the Ministry of Energy. The act lays down no deadline.
Is there a support scheme for producers?
Not under this act. Article 52 of the rules says expressly that the rules do not approve a support scheme and that it is to be approved separately, by Government decision, in compliance with State aid legislation.
What guarantees have to be provided?
Guarantees for the proper performance of the contract and for making good damage caused to the environment, provided for in Article 15(8) of Law no. 121/2024. The amount and the arrangements are set through the tender documentation and the concession contract, and the level may rise or fall as the project advances.
What happens once the farm reaches the end of its commercial life?
Between the end of commercial operation and the end of the concession, only the fee for the operating stage is due, on the areas still occupied by installations. The royalty, which is tied to revenue, no longer applies.

Errors and inconsistencies in the published text

  • The specific rules refer five times to an „anexa nr. 3”, annex no. 3, which does not exist. Article 41 requires the performance guarantee and the guarantee for making good damage caused to the environment to be provided „în tipul, cuantumul și condițiile prevăzute în prezentul articol și în anexa nr. 3”, in the type and amount and under the conditions laid down in that article and in annex no. 3; Article 48 sets the development-stage fee „în cuantumul și condițiile prevăzute în anexa nr. 3”, in the amount and under the conditions laid down in annex no. 3; Article 49 says that „cuantumul și modul de determinare sunt prevăzute în anexa nr. 3”, the amount and the method of determination are laid down in annex no. 3; Article 50 that „modul de calcul și de determinare a bazei de calcul se detaliază prin anexa nr. 3”, the method of calculation and of determining the basis of assessment is detailed in annex no. 3; and Article 55(d) requires the concessionaire to submit „raportările privind elementele care stau la baza determinării redevenței și taxelor, potrivit anexei nr. 3”, the reports on the elements underlying the determination of the royalty and the fees, in accordance with annex no. 3. The rules, however, have a single annex, the Methodology, and Article 58 of the rules together with Article 1(2) of the decision call it simply „anexa”, the annex. The same problem appears, more seriously, in Article 24 of the rules: the concession contract is concluded „pe baza contractului-model prevăzut în anexa nr. 1”, on the basis of the model contract laid down in annex no. 1, and annex no. 1 does not exist either. The result is that the fees have nowhere to be read and the contract has no model to be signed against, even though Articles 47 to 51 enter into force separately, 30 days after publication.
  • The date of the exchange rate is written in square brackets, like an unfinished drafting marker. Article 22(3) and Article 27(3) of the methodology provide, in identical terms, that the value of the fee „se stabilește în euro și se achită în moneda națională, la cursul de schimb al Băncii Naționale a României valabil la data de [31 decembrie] a anului calendaristic pentru care se datorează taxa”, is set in euro and paid in the national currency, at the National Bank of Romania exchange rate in force on [31 December] of the calendar year for which the fee is due. Square brackets are not a punctuation mark used in Romanian legislative drafting to set off a date; in drafting practice they mark an element that is still undecided. Since the fees are tax claims falling due on 30 March of the following year, and the leu-euro rate moves, the taxpayer cannot establish with certainty which rate applies, and the tax authority cannot check a conversion against a date left provisional.
  • The „premiul de concesiune”, the concession premium, appears in the list of financial obligations and nowhere else. Article 6(2)(e) of the methodology lists it among the financial obligations applicable to concessions, alongside the royalty, the two fees and the guarantees. Unlike those, which each have a chapter of their own, the concession premium is not defined in Article 4, has no article on how it is calculated, has no amount and is not mentioned again anywhere in the methodology or in the rules. It cannot be established whether it is due, who owes it, or how much it is.

Editorial analysis

The act solves the problem that had in practice been blocking offshore wind energy in Romania: the absence of a price. Since 2024 there has been a law, since 27 August 2026 there has been a map, and since 31 August there is also an invoice. That is the right order, and the speed with which the last two acts followed one another, four days, shows that the Ministry of Energy is working on a package rather than on scattered acts.

The arithmetic, though, shows where the State’s money actually comes from. The three perimeters in Government Decision no. 664/2026 add up to 948 km². If all of them were in the development stage at the same time and the works covered the entire area, the fee would bring in 758,400 euro a year; during the operating stage, again over the whole area, the theoretical ceiling would be 1,422,000 euro. In reality the fee is calculated on the area where works are actually carried out, and during operation on the built-up area, which in a wind farm is a small fraction of the perimeter, because the turbines stand hundreds of metres apart. In other words, the area fees are a symbolic sum measured against a 3.1 gigawatt project, and the only thing that matters financially for the State is the 0.75% royalty. That starts running only at the first commercial delivery, that is years from now.

The second thing that emerges from reading the articles together is that the act places the investor’s obligations ahead of the State’s. What the concessionaire pays is known to the last decimal. What the State pays, through the support scheme in Article 8 of Law no. 121/2024, is not known at all, and Article 52 of the rules confines itself to saying that the scheme is approved „distinct”, separately. For an offshore project the final investment decision turns on exactly that scheme, not on a fee of 1,500 euro per square kilometre. Publishing the fees without the scheme means that the predictable side of the equation is the one that decides nothing.

A third observation concerns the asymmetry of the deadlines. The concessionaire has firm deadlines everywhere: quarterly reports, an annual report by 31 March, declaration and payment by 30 March, guarantees kept valid throughout. The State has none. The Ministry of Energy sets „momentul lansării fiecărei proceduri competitive”, the moment each competitive procedure is launched, on the basis of four criteria, one of which, grid connection capacity, depends on a third actor, the transmission and system operator, which appears in the rules with no scheduling obligation whatsoever. An investor can know exactly how much it will pay, but cannot know in which year it will be able to bid.

What should be changed

  • Correct renumbering of the annex, before 30 September 2026. Three of the five references to „anexa nr. 3”, those in Articles 48, 49 and 50, concern precisely the articles that enter into force on that date, and the reference to „anexa nr. 1” blocks the signing of the concession contract in the form the rules provide for. A corrigendum published by then would prevent the first application of the fees from resting on texts that point nowhere.
  • A fixed date for the exchange rate, without brackets. If the intention is 31 December of the reference year, the text should simply say so. If the intention was the rate on the payment date, likewise. Either is better than a date left provisional in an act that generates tax claims.
  • A deadline for the support scheme. Without one, the offshore package remains half finished: complete rules on what the State collects, nothing on what it guarantees. A deadline of even six months would give the market a horizon for the investment decision.
  • An indicative tender calendar, published by the Ministry of Energy. The four criteria in Article 57 describe what the Ministry weighs up but produce no predictability at all. A list of the perimeters and the estimated launch quarter, updated periodically, would cost one page and would change the way bidders prepare.
  • Minimum thresholds for the environmental guarantee, written into the methodology. Today the guarantee for making good environmental damage is set entirely through the tender documentation. A minimum threshold linked to installed capacity or built-up area would take out of the commercial negotiation precisely the component that protects a public interest rather than a contractual one.

Original text of the legal act

The text below is reproduced in Romanian, the official form of publication.

The full text, as published in the Official Gazette of Romania

Official Gazette of Romania no. 731 and no. 731 bis of 31 August 2026 8 pages PDF, 75 KB the act starts on page 6

Open the official PDFDownload the PDF

The other editions cited: nr. 731 bis/2026

The viewer is not shown on small screens. Use the buttons above to open or download the file.

This article is for informational purposes only and does not constitute legal advice. For specific situations, consult a licensed attorney or tax advisor.