In brief

  • The deadline for completing investments under the renewable self-consumption programme financed by the Modernisation Fund is now set at 31 December 2028. The date covers installation, commissioning and grid connection, not merely the signing of the contract.
  • The guide no longer ties completion to a single deadline for the whole programme: each competitive bidding procedure launched by Romania’s Ministry of Energy will set its own completion date, which nevertheless cannot go beyond 31 December 2028.
  • The amendment touches nine places in the guide, including the annexes with the funding application, the beneficiary’s declarations and the annual expenditure plan. Among other things, the beneficiary signs an undertaking to finance completion from its own resources if the project is not ready in time.
Act: Order ME No. 765/2026
Published: Official Gazette No. 633 of 31 July 2026
In force from: 31 July 2026

The programme that lets companies and institutions build their own renewable electricity capacity for their own consumption now has a clear cut-off date, repeated throughout the document: 31 December 2028. Through Order No. 765/2026, Romania’s Ministry of Energy amended the specific guide for the Modernisation Fund financing line dedicated to self-consumption, approved in 2024. It is the state’s second move in the same direction within a short period, after the law allowed quantitative offsetting of electricity produced with solar panels for household consumers, a sign that self-consumption policy is settling on two distinct layers: direct support for large investments and billing mechanisms for small ones.

The Modernisation Fund is a European instrument for financing the energy transition, and the self-consumption line operates under a state aid scheme approved by Order No. 355/2024 of the Minister of Energy. The specific guide, approved by Order No. 356/2024 and published in Official Gazette No. 387 and 387 bis of 25 April 2024, is the document that states concretely who may apply, which costs are reimbursed and how long the investment may take. It is precisely this last element that has now been rewritten.

The new wording in chapter 1 point 1.1 is the key mechanism: completion of the investments, meaning installation, commissioning and grid connection, must take place by the date set out in each competitive bidding procedure launched and published on the ministry’s website, and may not exceed 31 December 2028. In other words, the real deadline becomes variable from one call to another, but it has an absolute ceiling.

The order was signed on 24 July 2026 by the interim Minister of Energy, Ilie-Gavril Bolojan, and entered into force on publication, on 31 July 2026. Implementation falls to the General Investment Directorate within the Ministry of Energy.

What it changes in practice

The first effect concerns the calendar. An applicant filing a funding application now knows that the whole project timeline, from design to the commissioning acceptance report, must fit before 31 December 2028. The date does not refer to the end of construction works but to the moment when the installation is commissioned and connected to the grid, which also covers the waiting time for the distribution operator’s approvals.

The second effect is financial and concerns the eligibility period for expenditure. The amended guide states that only costs incurred and paid between the date the funding application is filed with the ministry and the completion date set in the bidding procedure, at the latest 31 December 2028, will be reimbursed. Design costs, meaning the pre-feasibility study, the feasibility study or the technical design, and the purchase of land may be incurred earlier, but they are not reimbursed from the Modernisation Fund. This follows from the “start of works” principle in Article 2 of Regulation (EU) No 651/2014, which makes state aid conditional on a genuine incentive effect.

The third effect concerns assumed risk. Annex No. 3 has been amended so that the beneficiary declares it will secure, from other lawfully constituted sources of financing, the money needed to complete the project if it is not fully implemented by 31 December 2028. Missing the deadline is therefore not only a reporting issue but a financial commitment the applicant signs at the filing stage.

The fourth effect is administrative. The annual expenditure plan in Annex No. 7 is now drawn up for an implementation period that closes in 2028, with columns from 2023 to 2028. Anyone whose financing schedule stretched beyond that horizon has to compress it.

What has changed compared with the previous situation

In the nine places now amended, the guide approved in 2024 contained references to a completion deadline that no longer matched the programme’s real calendar. Order No. 765/2026 aligns them all to the same reference point, 31 December 2028, and additionally introduces the notion of a deadline set per call for projects.

The change of logic matters. Previously an applicant looked at a date written in the guide. From now on it must look at two things at once: the date in the documentation of the competitive bidding procedure it enters, and the general ceiling in the guide. If the call says 30 June 2028, that is the date that counts for that applicant, even though the guide allows until the end of the year.

The place where the information is found has changed too. Specific completion dates are published on the Ministry of Energy’s website together with each procedure, not in the Official Gazette. For a potential beneficiary, that means monitoring the ministry’s page becomes part of preparing the file.

Nothing has changed regarding the eligibility of applicants, the aid intensity or the types of investment accepted. The order is strictly about the calendar, the eligibility period for expenditure and the forms that reflect them.

Advantages and disadvantages

What it improves

  • It removes inconsistencies between the body of the guide and its annexes: the same date now appears in all nine places, which lowers the risk of a file being rejected over a contradictory deadline.
  • It gives the ministry real flexibility: a call launched late can carry a tighter deadline and one launched early a more relaxed one, without amending the guide each time.
  • It clarifies what completion means: installation, commissioning and grid connection, not merely acceptance of the works.
  • It expressly settles the treatment of design costs and land purchase, an area where applicants frequently erred by assuming retroactive reimbursement.

What remains a problem

  • The 31 December 2028 ceiling gets tighter with every month that passes. An industrial-scale self-consumption project needs permits, a grid connection approval and equipment deliveries, and upstream delays are not under the beneficiary’s control.
  • The risk of overshooting falls entirely on the beneficiary, who signs an undertaking to finish the project from its own resources. For a small company or a local authority with a rigid budget, that commitment can be discouraging.
  • A deadline that varies per call adds a source of uncertainty: until the documentation is published, the applicant does not know which date it is actually working towards.
  • The order provides no extension procedure for objective causes, so an external administrative blockage translates directly into loss of funding.

Practical advice

  1. If you are preparing a funding application: build the activity schedule backwards from the end, not from the start. Set the commissioning acceptance at least three months before 31 December 2028 and only then arrange the upstream stages.
  2. If you already have a project under implementation: check whether your schedule extends beyond 2028 in any document, including the annual expenditure plan in Annex No. 7. The columns now run to 2028, so a plan with expenditure in 2029 is no longer compliant.
  3. If you have already commissioned feasibility studies or bought land: do not include those amounts in the costs claimed for reimbursement if they were paid before the application was filed with the ministry. They are permitted but not eligible.
  4. If you are waiting for a call to open: watch the Ministry of Energy’s website, not only the Official Gazette. The completion date applicable to your call is published in the documentation of the competitive bidding procedure.
  5. If you are a municipality, a hospital or another public institution: prepare in good time the decision to cover any shortfall from your own budget, required by the declaration in Annex No. 3. Approving such a budget commitment takes time, and the declaration is filed together with the application.
  6. If you are negotiating with an equipment supplier: write delivery deadlines and penalties into the contract, aligned with the project completion date. In your relationship with the funder, the delay risk stays with you.

Frequently asked questions

Which funding programme does this order affect?
The support line for investments in new capacity to produce electricity from renewable sources for self-consumption, financed from the Modernisation Fund. The state aid scheme was approved by Order No. 355/2024 of the Minister of Energy, and the specific guide by Order No. 356/2024.
What is the completion deadline now?
The date set in the documentation of each competitive bidding procedure, with an absolute ceiling at 31 December 2028. Completion includes installation, commissioning and connection to the grid.
Which costs are eligible for reimbursement?
Those incurred and paid from the date the applicant files the funding application with the Ministry of Energy until the investment completion date set in the competitive bidding procedure, at the latest 31 December 2028.
May I start the design work before filing the application?
Yes. The guide expressly allows activities such as the pre-feasibility study, the feasibility study, the technical design or the purchase of land to be carried out before the eligibility period begins. Their cost will not, however, be reimbursed from the Modernisation Fund.
What happens if I do not finish the project by 31 December 2028?
Through the declaration in Annex No. 3, the beneficiary undertakes to secure from other lawfully constituted sources of financing the money needed to complete the project in that situation. The order provides no procedure for extending the deadline.
Why is the deadline not the same for every project?
Because the amended guide ties the completion date to each individual competitive bidding procedure. The ministry can thus adapt the deadline to the moment the call is launched, while still respecting the ceiling in the guide.
From when do the amendments apply?
From the date of publication in the Official Gazette of Romania, Part I, that is 31 July 2026, under Article II of the order.
What is the “start of works” principle invoked in the order?
It is the rule in Article 2 of Regulation (EU) No 651/2014 on state aid, under which public support must have a genuine incentive effect. That is why the eligibility period for expenditure begins when the funding application is filed, and not earlier.
How many provisions of the guide were amended?
Nine: the seventh paragraph of chapter 1 point 1.1, bullet 2 of point 1.8 subpoint 1, letters d) and f) of chapter 2 point 2.2, two passages of point 2.3, letter (b) of Annex No. 1.a, letter d) of Annex No. 2.1, bullet 6 of Annex No. 3 letter B, paragraph (6) of Article 2 of Annex No. 5 and table 5 of Annex No. 7.

Original text of the legal act

The text below is reproduced in Romanian, the official form of publication.

Show the full legal textHide the full legal text

ORDIN nr. 765 din 24 iulie 2026

privind modificarea Ghidului specific — Sprijinirea investițiilor în noi capacități de producere a energiei electrice produse din surse regenerabile pentru autoconsum, aferentă Fondului pentru modernizare, aprobat prin Ordinul ministrului energiei nr. 356/2024

EMITENT: MINISTERUL ENERGIEI

Publicat în: MONITORUL OFICIAL nr. 633 din 31 iulie 2026

Având în vedere:

— art. 6 alin. (1) lit. f) din Ordonanța de urgență a Guvernului nr. 60/2022 privind stabilirea cadrului instituțional și financiar de implementare și gestionare a fondurilor alocate României prin Fondul pentru modernizare, precum și pentru modificarea și completarea unor acte normative, aprobată cu completări prin Legea nr. 376/2023, cu modificările și completările ulterioare;

— Ordinul ministrului energiei nr. 355/2024 pentru aprobarea Schemei de ajutor de stat privind sprijinirea investițiilor în noi capacități de producere a energiei electrice produse din surse regenerabile pentru autoconsum, aferentă Fondului pentru modernizare, cu modificările ulterioare;

— Referatul Direcției generale investiții nr. 199.453 din 3.07.2026 privind necesitatea modificării Ghidului specific — Sprijinirea investițiilor în noi capacități de producere a energiei electrice produse din surse regenerabile pentru autoconsum, aferentă Fondului pentru modernizare, aprobat prin Ordinul ministrului energiei nr. 356/2024,

în temeiul prevederilor art. 10 alin. (6) din Hotărârea Guvernului nr. 316/2021 privind organizarea și funcționarea Ministerului Energiei, cu modificările și completările ulterioare,

ministrul energiei, interimar, emite prezentul ordin.

Articolul I — Ghidul specific — Sprijinirea investițiilor în noi capacități de producere a energiei electrice produse din surse regenerabile pentru autoconsum, aferentă Fondului pentru modernizare, aprobat prin Ordinul ministrului energiei nr. 356/2024, publicat în Monitorul Oficial al României, Partea I, nr. 387 și 387 bis din 25 aprilie 2024, cu modificările ulterioare, se modifică după cum urmează:

1. La capitolul 1 punctul 1.1, paragraful al 7-lea se modifică și va avea următorul cuprins:

„Finalizarea investițiilor, respectiv instalarea, punerea în funcțiune și conectarea la rețea, se va realiza până la data prevăzută în cadrul fiecărei proceduri de ofertare concurențială ce va fi lansată și publicată pe site-ul ME conform prevederilor legale și nu poate depăși data de 31.12.2028.”

2. La capitolul 1 punctul 1.8 subpunctul 1, marcatorul 2 se modifică și va avea următorul cuprins:

„○ descrierea proiectului, inclusiv data începerii și a finalizării acestuia (data finalizării nu va depăși data stabilită în cadrul fiecărei proceduri de ofertare concurențială), respectiv în cadrul acestui apel data de 31.12.2028;”.

3. La capitolul 2 punctul 2.2, literele d) și f) se modifică și vor avea următorul cuprins:

„d) Perioada de implementare a proiectului se încadrează în perioada de eligibilitate a cheltuielilor, respectiv între data la care solicitantul depune cererea de finanțare la ME și data preconizată de finalizare a proiectului, dar nu poate fi mai târziu de 31.12.2028, cu respectarea principiului «demararea lucrărilor» prevăzut la art. 2 din Regulamentul (UE) nr. 651/2014. Anumite activități legate de proiect [de exemplu: proiectare (studiul de prefezabilitate, studiul de fezabilitate, proiectul tehnic etc.) și achiziția de teren etc.] pot fi realizate înainte de data de început a eligibilității, respectiv data la care solicitantul depune cererea de finanțare la Ministerul Energiei, însă acestea nu vor fi eligibile pentru rambursarea din Fondul pentru modernizare;

A se vedea secțiunea Activități previzionate din cererea de finanțare.

…………………………………………………………………………………..

f) Durata de implementare a proiectului nu depășește data de 31.12.2028;

A se vedea secțiunea Activități previzionate din cererea de finanțare.”

4. La capitolul 2 punctul 2.3, paragraful al patrulea și punctul 1) de la paragraful al șaselea se modifică și vor avea următorul cuprins:

„Cheltuielile eligibile pentru rambursare sunt efectuate în perioada de eligibilitate, respectiv între data la care solicitantul depune cererea de finanțare la ME și data preconizată de finalizare a proiectului, dar nu poate fi mai târziu de 31.12.2028, cu respectarea principiului «demararea lucrărilor» prevăzut la art. 2 din Regulamentul (UE) nr. 651/2014.

…………………………………………………………………………………..

1) să fie efectuată și plătită de la data la care solicitantul depune cererea de finanțare la ME, dar nu mai târziu de data de finalizare a investiției prevăzută în cadrul procedurii de ofertare concurențială, respectiv data de 31.12.2028;”.

5. La anexa nr. 1.a punctul 1 pentru aplicarea art. 6 „Efectul simulativ, alin. 1 și 2”, litera (b) se modifică și va avea următorul cuprins:

„(b) descrierea proiectului, inclusiv data începerii și a finalizării acestuia (data finalizării acestuia nu va depăși data de 31.12.2028);”.

6. La anexa nr. 2.1 secțiunea „Eligibilitate” litera B — „Eligibilitatea proiectului”, litera d) se modifică și va avea următorul cuprins:

„d) Durata de implementare a proiectului nu depășește data de finalizare a investiției prevăzută în cadrul procedurii de ofertare concurențială, respectiv 31.12.2028;”.

7. La anexa nr. 3 litera B, marcatorul 6 se modifică și va avea următorul cuprins:

„ să asigure din alte surse de finanțare legal constituite finanțarea necesară pentru finalizarea proiectului în situația în care acesta nu va fi implementat în integralitate până la data de 31.12.2028;”.

8. La anexa nr. 5 articolul 2, alineatul (6) se modifică și va avea următorul cuprins:

„(6) Perioada de implementare a proiectului se încadrează în perioada de eligibilitate a cheltuielilor, respectiv între data la care beneficiarul a depus cererea de finanțare și data procesului-verbal de recepție a punerii în funcțiune a investiției, în conformitate cu graficul de activități, dar nu mai târziu de data de 31.12.2028.”

9. La anexa nr. 7 punctul 5, tabelul 5 se modifică și va avea următorul cuprins:

„5. Buget — Plan anual de cheltuieli

TABEL 5
— lei —

An(4): 2023 | 2024 | 2025 | 2026 | 2027 | 2028
Cheltuieli

(4) Planul anual de cheltuieli se va întocmi pentru perioada de implementare a investiției, care nu va depăși data de 31.12.2028.”

Articolul II — Prevederile prezentului ordin intră în vigoare la data publicării în Monitorul Oficial al României, Partea I.

Articolul III — Direcția generală investiții din cadrul Ministerului Energiei va duce la îndeplinire prevederile prezentului ordin.

Ministrul energiei, interimar,
Ilie-Gavril Bolojan

București, 24 iulie 2026.
Nr. 765.

Sursa: Monitorul Oficial al României, Partea I, nr. 633 din 31 iulie 2026.

This article is for informational purposes only and does not constitute legal advice. For specific situations, consult a licensed attorney or tax advisor.